Latest update on Brighouse town centre works including what work has already taken place

The Brighouse Town Deal Board is thanking everyone for their patience and understanding as work on the major regeneration project continues.

For the next 18 months, there will be a series of road closures, changes to traffic flow and the suspension of some on-street parking spaces as part of the Brighouse Town Deal project.

Esh Construction, which is carrying out the work on behalf of Calderdale Council and the Town Deal Board, has been keeping everyone updated with what is happening behind the barriers on the website at www.brighousedeal.co.uk

One of the most noticeable changes is on Hutchinson Lane, between Gooder Street and Commercial Street, where the road has been paved with the sandstone which will be a familiar sight across the town centre.

Aerial photographs from late February 2026 of Commercial Street.placeholder image
Aerial photographs from late February 2026 of Commercial Street.

A spokesperson said this route will provide “a much more attractive link” between the town centre, bus station and Parsonage Lane car park.

Work on Church Lane to excavate and lay concrete is continuing and will soon be finished with the same sandstone that has been laid on Hutchinson Lane.

On Commercial Street, excavation work has been taking place and the granite kerb installed between Church Lane and Hutchinson Lane showing how the loading and parking bays will be marked in the town centre.

On Market Street, excavation work to make the area ready for the kerb installation has been taking place.

Hutchinson Lane.placeholder image
Hutchinson Lane.

On Thornton Square and Briggate, the large cell of ten tree pits has been installed.

Work is currently underway on Commercial Street, Thornton Square/Bethel Street, Market Street and West Park Street.

On Commercial Street the team will be removing the existing pavement surface and beginning to install the new pavement finishes, made up of two different types of paving slabs and granite.

There will also be planting of trees towards the bottom of Hutchinson Lane and outside Czerwiks.

Aerial photographs from late February 2026 of Thornton Square.placeholder image
Aerial photographs from late February 2026 of Thornton Square.

Work to excavate the tree pits in the west end of Bethel Street (towards Thornton Square) will continue with concrete pavement work across the new tree pits in preparation for the new paving to be installed.

The granite kerb will be installed on Market Street and planting of trees will take place.

Work is set to begin on West Park Street with the removal of the existing footway and kerb.

Work will then be taking place on Commercial Street with paving installed to the remaining section of the north footway to the junction with Gooder Lane.

Work on Commercial Street.placeholder image
Work on Commercial Street.

Esh will begin work on the south side of Commercial Street (from Costa outside Wellington Arcade to Papa John's and the western footway of Market Street).

While on Briggate and in Thornton Square, the preparation work for paving will continue.

The town centre improvements are funded from Brighouse’s £19.1million Town Deal funding.

For more information on Brighouse Town Deal, visit www.brighousedeal.co.uk